Item

Job Description

Contract Sum (RM)

Client

Date Start

Date Finish

Remark

1.

Temerloh – Jerantut road widening

  • Casting of Post Tension Beams

750,000.00

Genesis Sdn Bhd

Apr 2002

Apr 2003

Sub
Contractor

2.

Proposed Building and Completion of 125 units of Double Storey Houses at Lot No. 39714 & 39716, Section U5 Mukim Sungai Buloh, Shah Alam, Selangor.

8,362,225.50

Syarikat Usahasama Sdn Bhd(Client – World Wide Berhad)

Feb 2003

Mar 2004

Main
Sub
contractor

3.

Relocation of West Wing escalator at Sunway Pyramid

1,366,000.00

Sunway Pyramid Sdn Bhd

April 2003

July 2003

Sub
Contractor

4.

Proposed renovation works of new partition wall & associated works for tenant lots extension, for Sunway Pyramid Sdn Bhd

763,407.00 Sunway City Sdn Bhd

Nov 2003

Dec 2003

Sub
Contractor

5.

Proposed renovation works of upgrading existing ground floor Esprit’s corridor & Penang Street’s corridor & lift lobby for Sunway Pyramid Sdn Bhd

260,877.80 Sunway Pyramid Sdn Bhd

Nov 2003

Dec 2003

Sub
Contractor

6.

Proposed renovation works of supply, install & completion of fire rated corridor & storage compartment at LL2 Star Archery, Sunway Pyramid Sdn Bhd

318,249.00 Sunway Pyramid Sdn Bhd

Nov 2003

Dec 2003

Sub
Contractor

7.

Proposed renovation works of new partition wall & associated works for tenant lots extension for Sunway Pyramid Sdn Bhd

186,339.50 Sunway Pyramid Sdn Bhd

Nov 2003

Dec 2003

Sub
Contractor

 

 

 

 

 

 

 

 

 

 

 

 

8.

Cadangan Pembangunan Kinrara Estate Di atas Lot 3197, 3198, 1804, Mukim Petaling, Selangor untuk Tetuan Perumahan Kinrara Berhad. Reshaping of Existing Slope in View of Proposed Development at Phase B29

6,275,800.00

Perumahan Kinrara Berhad
(Client - I & P)

Oct 2004

May 2005

Main
Sub
contractor

9.

Cadangan Membina Jalan Sambungan (Missing Link) Jln Awan Besar ke Lebuhraya Shah Alam, Kuala Lumpur – Cadangan Membina ‘Ramp’ dari Jalan 2/149, Bandar Baru Sri Petaling ke Lebuhraya Shah Alam ke arah Cheras (Di persimpangan Bertingkat Awan Kecil), Kuala Lumpur Secara ‘Design & Build’

15,000,000.00

Amalgamated Metal Builders (M) Sdn Bhd
(Client –Dewan Bandaraya Kuala Lumpur)

June 2005

May 2006

Main
Sub
contractor

10.

Package 5 – Reinstate KESAS Median

312,500.00

 

Leighton Contractors (M) Sdn Bhd

Sept 2006

Nov 2006

Sub
Contractor

11.

North-South Expressway Proposed Third Lane Widening Between Tanjong Malim And Slim River (Package 4). Job. No. PLUS/WU/UUD/0425/C2,C3/05

25,179,376.00

Amalgamated Metal Builders (M) Sdn Bhd

Dec 2005

February 2007

Main
Sub
Contractor

12.

Cadangan Pembangunan Kediaman Puncak Bangi Fasa 1b Yang Mengandungi 48 Unit Rumah Berkembar 21/2 Tingkat, Pusat Bandar, Bandar Baru Bangi, Mukim Kajang, Daerah Hulu Langat, Selangor Darul Ehsan

17,287,500.00

Syarikat Usahasama SM Sdn Bhd
(Client –Perbadanan Kemajuan Negeri Selangor)

Jun 2007

July 2009

Main
Sub
Contractor

13.

Cadangan Membina Jejambat Menghubungkan Jalan Mahkota, Taman Maluri dan Jalan 4/91, Taman Shamelin Perkasa

59,500,000.00

Syarqiah Holdings S/B. (Client – Dewan Bandaraya Kuala Lumpur

March 2009

July 2012

Main
Subcontractor

14.

Cadangan Membina Dan Menyiapkan 1 Unit Gudang Satu Tingkat Di Atas Lot PT 56396, (lot Lama 799), Jalan KPB 2, Kawasan Perindustrian Budiman, Mukim Cheras, Daerah Hulu Langat, Selangor Darul Ehsan

3,347,965.03

Mestika Pujangga S/B

July 2012

April 2013

Main Contractor

15.

Proposed Development of KLIA 2 And Associated Works At Kuala Lumpur International Airport, Sepang, Selangor

11,000,000.00

SWA Water Malaysia S/B  (MAHB)

July 2013

April 2013

Main Contractor

16.

Proposed Solar Farm At Kuala Lumpur International Airport, Sepang Selangor DarulEhsan

7,955,000.00

Sime Darby Offshore Engineering Sdn. Bhd.

April 2013

Sept 2013

Main Contractor

17

Cadangan Membina Sebuah PencawangMasuk Utama 275/11 KV diatas Lot 2040, 2182 Dan Sebahagian  Lot 2028 Dan 2029, Mukim Jeli Daerah Jeli, Kelantan Darul Naim

2,248,388.11

Trangrid Resources Sdn. Bhd.

May 2014

October 2014

Main Contractor

18

Proposed Relocation Of KTMB Diesel Tanks From KL Sentral Depot To KL Old Station (South End Of Platform 4)

450,000.00

Gelanggang Harapan Construction Sdn. Bhd. (A Subsidiary Of MRCB Group)

April 2015

November 2015

Main Contractor

19

Proposed demolition of existing 2 storey building and rebuilding a 7 storey budget hotel containing basement floors, semi-basement floors, bedrooms area at level 2to 6 on Lot Nos. 602, 603, 604, 605, 606 and 607 in Section 19, JalanPuduLama in City of Kuala Lumpur.

16,286,964.90

Money Bloom Sdn. Bhd.

Sept 2014

Dec 2016

Main Contractor